Beja: PCP delivered the Assembly of the Republic Draft resolution on Hospital.


Projeto de Resolução sobre a construção da 2ª fase do Hospital Distrital de Beja foi ontem entregue pelo Grupo Parlamentar do PCP na Assembleia da República.

The Draft Resolution, It proposes measures to be initiated procedures for the remodeling and expansion of the hospital Beja, having communist exposed the reasons that led to his inauguration and we record full.

It is now almost 46 years since the process of "remodeling and expansion of the hospital Beja" first emerged, with the preparation of functional program and appropriate technical project, considering then have to date an urgent need to address shortcomings of the initial project that was implemented in October 1970.

Over the years and up 2010, the functional program and technical project underwent changes introduced by successive governments, He has been enrolled in PIDDAC awaiting the availability of funds for the contract, seeking an application for co-financing to eligible value of approximately 25 (twenty five) million. What, It never materialized!

In view of the fact that there is a hospital in Beja evident dysfunctionality in terms of its facilities and the inherent difficulty in ensuring the same proper working order to provide the population covered a decent service and quality, ensuring accessibility conditions, comfort and security to them and to their professional, the need for such intervention was evident for many years, It is aggravating recently with increasing requirements associated with an improvement of care.

for these reasons, the issue of securing users and qualified professionals, It is one of the concerns of the region, can not be dissociated, respectively, the need to improve the conditions of access to the first and to the second work.

The situation has already occurred, despite the enormous efforts of health professionals working in hospital, It is continued lack of professionals and means to provide the public service under the National Health Service, as well as a continued weakening of primary health care.

is reinforced so the correctness of the remodeling and expansion of the hospital Beja does not cancel, before strengthens, the need to improve the current conditions of the hospital. Rest, its correctness came to be reflected in the widening of the support that was collecting on the populations, professionals and users for whom it was becoming increasingly clear need to remodel and expand the hospital, It is expected to improve various technical installations, imaging, relocation and adjustment of valences: outpatient, Gastroenterology, general emergency, pediatric emergency, Clinical pathology, Imunohemoterapia, operating room, intensive care unit and creating heliport operating in modern building with adequate conditions for the provision of quality health care, ensuring working conditions able to fix professionals in a region that has been battered by desertification of the territory as a result of policies that have been accentuating regional disparities.

After all this time (from 2004, year in which the funds were still enrolled in PIDDAC) is recorded, lamentably, the remodeling and expansion of the hospital has been delayed without being clarified and taken any implementation strategy, in the hospital master plan in question, by the successive governments.

The risk at this point arises, although we continue to observe mapping and registration of funds in the hospital investment plans, It is a continuation of the uncertainty and to take the will to complete a process already started by completing the appropriate functional program and project execution still need to set the timing of the launch of the tender and execution of the contract, cautioning the possibility of application to European funds.

At this point, it is absolutely essential that there is a clear definition of the overall investment amount (which as previously stated will be approximately 25 million), of its multiannual allocation and identification of the respective sources of funding, schedule and phasing of construction, and the procedures and to adopt measures to simplify and facilitate the implementation of the investment.

In these terms, under subparagraph b) Article 156 of the Constitution and b) do n.º 1 Article 4 of the Rules, Members of the PCP's Parliamentary Group propose that the National Assembly adopt the following:

The Parliament decides, under paragraph 5 Article 166 of the Constitution, recommend to the Government to take the necessary measures to be initiated within 180 day procedures for the remodeling and expansion of the hospital Beja, namely

Assigning formally to the Board of Directors of the Hospital José Joaquim Fernandes competence to trigger the necessary procedures to the beginning of the remodeling and expansion of the hospital process;

Setting a schedule for the refurbishment and expansion of the Hospital to ensure the opening of the tender within a period of twelve months, taking the total amount of multi-year investment to be made and the respective sources of funding;

Setting the phasing of the construction so that beginning the procedures necessary to launch the venture and licensing project, allowing the carrying out of the respective expenditure;

Mobilizing EU funds for the remodeling and expansion of the hospital;

Creating a public access mechanism for citizens to all the updated information on the procedures for the remodeling and expansion of the hospital, in particular through electronic means.


Share This Post On
468x60.jpg